Curley’s Bay Reserve update

Date of the Event or Workshop: -

Project Update from Culburra Beach Skate Park Project Facebook Page  – 26th October 2016
We have finally received our water line investigation and location report for the newly discovered water trunk line across the Curley’s Bay Reserve site by council and Shoalhaven Water.
Our engineers have reviewed the detail and have adjusted our park design to accommodate the water lines, no major changes to layout or design. This has delayed our community park project but we are working hard to get the timelines and schedule of works back on track for completion in early 2017.
Another update very soon

 

preliminary-engineering-report

curleys-beach-layout